This project comprised preparation of a P90 cost estimate for the upgrade Mount Lindesay Arterial Road and Compton Road intersection, Sunnybank Hills. The upgrade includes placing high friction road surfacing, removal of medians, and the installation of new pavement markings and signage. 

Geleon provided the following services:

  •  Identified and prepared a schedule of standard work items in accordance with  Transport and Main Roads (TMR) specifications;
  •  Undertook a quantity take-off and prepared a bill of quantities;
  •  Prepared a P90 cost estimate in accordance with the TMR Project Cost Estimating  Manual;
  •  Performed a probabilistic Monte Carlo simulation using @Risk to quantify the  construction contractors, principles and project risks; and
  •  Prepared a report detailing the estimating process, methodology and presented the  estimated costs. 

 

Quick Facts

Client

Harrison Infrastructure Group

Date

November 2015

Location

Sunnybank Hills, Qld

Project Value

$0.5M