Engineers. Managers. Planners

Jubilee Terrace & Waterworks Road – Options Analysis

Jubilee Terrace & Waterworks Road – Options Analysis

This options analysis project looked at upgrading Jubilee Terrace between Devonshire Street and Stewart Road, including the major intersection with Waterworks Road. The upgrade of this local link is seen as critical to achieving the needs and functional outcomes of the corridor and includes upgrading two major intersections and three minor intersections. Works associated with the upgrade involve earthworks, pavement construction, drainage structures, traffic signals, road lighting and pavement markings.

Geleon provided the following services:

  •  Identified and prepared a schedule of standard work items in accordance with  Transport and Main Roads (TMR) specifications;
  •  Undertook a quantity take-off and prepared a bill of quantities; and
  •  Prepared three comparative cost estimates in accordance with the Transport and  Main Roads Project Cost Estimating Manual. 

     

Quick Facts

Client

Lambert & Rehbein

Date

June 2016

Location

Ashgrove, Qld

Project Value

$13.5M


Project Queries...